MASON CITY – Progress continues at the NIACC Student Housing facility. Regular updates will be sent to help keep you informed about the status of the project.
Work in progress
- Setting wall panels, floor and roof trusses at the south half – East Wing
- Preparation for the installation of the roof membrane on south half – East Wing
- Underground utility work – East & West Wing
- Masonry work on center stairwell tower and elevator shaft – East Wing
- Forming, pouring footings and foundations walls – West wing
- Electrical rough-in work at the East Wing – south half
- Pouring slab-on-grade at the West Wing – south half
In the next four weeks the following work is scheduled:
1. Begin installation of site retaining walls
2. Complete setting of steel at the SE stair tower
3. Complete setting of equipment at the East Wing mechanical room
4. Complete roof sheathing / blocking at the East Wing
5. Complete setting structural steel and precast at the East Wing
6. Complete underground utilities at the East Wing – north half
7. Complete backfilling at the East Wing
8. Complete pouring slab on grade at the East Wing – north half
9. Complete setting CMU at NE stair tower and fire wall
10. Begin installing moisture barrier at the East Wing – south half
11. Begin mechanical room piping / welding at the East Wing
12. Complete frost walls and footings at the West Wing
13. Begin setting wall panels at the West Wing – south half
14. Complete metal studs and sheathing at the West Wing
15. Complete pouring footing and foundation walls at the North Link
16. Begin underground utilities at the North Link