From the Mason City School District:
John Adams Middle School renovation:
Phase 3A – Larson Contacting
o Interior work is complete.
o Exterior sheet metal and landscaping should be complete by the end of the month.
Phase 3B – Henkel Construction
2nd Floor
o Lockers are being installed.
o Casework will begin next week.
o Restroom tile is complete.
o Ceiling tile and flooring will start in the next two weeks.
o Lighting and electrical devices are being installed.
o Communication cabling has started and will take a few weeks to complete.
1st Floor
o Drywall at the east side has started.
o Painting of drywall at the west side will start next week.
o Mechanical units and temperature control equipment are being piped and insulated.
o Terrazzo restoration in John Adams is complete.
o New gymnasium windows are installed and new roof is almost complete at gym and pool.
High School Music
o Exterior brickwork is almost complete.
o Demolition in music rooms has begun and will take a few more weeks to complete.
o New mechanical mezzanine structure will start being built by the end of April.
Phase 4 FEMA Safe Room – Holland Contracting
o Majority of interior brick at large multipurpose room is complete.
o 2nd Floor hollow-core precast has been set and 2nd Floor masonry walls have started.
o Concrete floors have been placed at the restrooms. Concrete floors will continue at the corridors and Stage area during the next two weeks.
o 2nd Floor topping slabs will begin within the next two weeks.
o Electrical conduit and ductwork is being installed at Stage area.
Phase 5 MCHS Two-story – Dean Snyder Contracting
o Material submittals are being reviewed.
o Construction will begin in June.
For additional information and pictures of the Secondary Campus renovations go to: www.masoncityschools.org and click on the Construction News Banner.