Streetscape work continues in Mason City, week of June 6th

General Notes:
Intersection at 4th and Federal will be closed starting today for additional utility work. The 3rd Street intersection will be OPEN during the time this work is being completed. Alliant Energy will continue work in Enterprise Alley on both gas and electric utilities. No service interruptions are expected; however, Alliant will take responsibility for contacting property owners if interruption of service is necessary.

Again, all work start dates are ‘weather permitting’.
Week beginning Monday, June 6

McKiness
Coring out the sidewalk area along the west side of Federal between 1st and 2nd
Streets will be completed on the ½ block that remains.
Light pole bases will be backfilled from 2nd ñ 4th Street.
Street grading will begin either from 2nd ñ 4th Street or on State Street in front of
the Park Inn Hotel to prepare for street paving.

Wicks
Concrete work will be completed in the Plaza.
The concrete sidewalk work along the west side of Federal between 1st and 2nd
Streets will be completed.

Country Landscape
Installation of pavers will begin in the Plaza.
Pavers will be installed in the sidewalk along the west side of Federal between 1st
and 2nd Streets.

Blazek
Electrical work will continue between 2nd and 4th Streets.

Stay alert and stay safe in the work zone!
Please avoid wet concrete areas!
Watch for tripping hazards!
THANK YOU FOR YOUR CONTINUED PATIENCE!!|

0 0 votes
Article Rating
Subscribe
Notify of
guest

0 Comments
Inline Feedbacks
View all comments

Even more news:

Copyright 2024 – Internet Marketing Pros. of Iowa, Inc.
0
Would love your thoughts, please comment.x
()
x